Tidal traffic management planned for Menai Suspension Bridge work
A six-day arrangement was planned from 9 March while equipment was prepared for underdeck work.
The Welsh Government said crossbeam work on Menai Suspension Bridge had been completed and that the next phase would involve lifting the Aerotruss scaffold to the underdeck.
It said tidal-flow traffic management would start on 9 March for about six days, with Anglesey-to-mainland travel from 7am to 1pm and mainland-to-Anglesey travel from 1pm to 7pm.
The east footpath was to remain open, while cyclists were asked to dismount. The government said the 7.5-tonne weight limit remained essential while work continued.